Analysis of Human Resource Factors Influencing the Delivery of Construction Projects in Shiraz
Subject Areas : Journal of Building Information Modeling
Roozbeh Aghamajidi
1
,
AMIR VAKILI
2
,
Gohar Varamini
3
1 -
2 - civil department , islamic azad university , beyza , branch , Iran
3 -
Keywords: : Development. Reviewingconstruction projects, Delays, Employer, Human resources,
Abstract :
Construction delays are a chronic problem in Shiraz, marring schedules, pushing up costs and putting a strain on the regional economy. This report explores the drains on timeliness, focusing on two key players: employers and the workforce. Through 180 major housing projects across the city, the research reveals how poor scheduling, workforce mismanagement and employer decision-making more often stymie progress. filtered out through surveys and site visits the opinions of 60 project supervisors the variety of whom was supposed to accurately reflect the wider landscape and scrutinized their responses to figure out where errors occur.T he findings stung: 43% of the time, delays return to the workforce things like skill gaps or bad coordination and 37% of the time to employers things like delayed approval or budget mistakes. These are not just figures: They represent real-world frustrations for workers, developers and communities left in limbo for homes. By directly addressing these human-centered issues such as enhancing training, simplifying decisions or optimizing resource use the study claims Shiraz can unlock its construction bottlenecks.
Ahmadi, A. (2006). Economic impacts of project delays in construction. Journal of Construction Management, 12(3), 45–58.
Ahmadi, M. (2006). Economic and technical challenges in construction projects. Tehran, Iran: Construction Research Press.
Ahmadi, R. (2006). Reasons for delay of construction projects in Iran and ways of getting out [Master’s thesis, Iran University of Science and Technology].
Alavi, S., Rahman, M., & Smith, J. (2022). Digital transformation in construction: Reducing delays through BIM. Journal of Construction Engineering, 45(3), 234–248. https://doi.org/10.1016/j.jce.2022.03.004
Ansari, J. (2011). The impact of delays on the lifespan of construction projects. Journal of Urban Development, 45(3), 123–135.
Ansari, R. (2011). Lifecycle analysis of construction projects. Urban Development Review, 19(2), 112–125.
Ansari, V. (2011). Law of administrative contracts. Tehran, Iran: Daneshnegar Publications.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Carr, S., Francis, M., Rivlin, L. G., & Stone, A. M. (1992). Public space. Cambridge, England: Cambridge University Press.
Chen, L., Wang, Y., & Zhang, H. (2023). Adaptive project management for large-scale construction projects. International Journal of Project Management, 41(2), 112–125. https://doi.org/10.1016/j.ijproman.2022.12.003
Cowan, R. (2005). The dictionary of urbanism. Tisbury, England: Streetwise Press.
Doloi, H., Sawhney, A., Iyer, K. C., & Rentala, S. (2012). Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, 30(4), 479–489. https://doi.org/10.1016/j.ijproman.2011.10.004
Eshtehardian, E. (2010). Civil project crisis: Challenges and solutions. International Journal of Project Management, 28(4), 345–356. https://doi.org/10.1016/j.ijproman.2009.08.002
Eshtehardian, E., & et al. (2010). Investigating the causes of delays in the implementation of urban development projects considering the factors of project management in the 11th phase. [Conference proceedings unavailable for further details].
Fahimi, A. (2010). Factors contributing to delays in construction projects. Tehran, Iran: Engineering Press.
Fahimi, M. (2010). Mitigating delays in construction projects: A case study approach. Construction Management Journal, 18(4), 56–70.
Fahimizadeh, H. (2010). Investigating the causes of delays and consequences of delivery to dams in Khorasan Province [Master’s thesis, Shahid Beheshti University].
Fateh, M., & Valipour, A. (2017). Investigating the causes of delays in construction projects with emphasis on existing problems in human resource management. In Proceedings of the 2nd International Conference on Civil Engineering, Architecture and Crisis Management (pp. 1–11).
Flyvbjerg, B., Bruzelius, N., & Rothengatter, W. (2003). Megaprojects and risk: An anatomy of ambition. Cambridge, England: Cambridge University Press.
Huemann, M. (2010). Considering human resource management when developing a project-oriented company: A case study of telecommunications. [Publication details incomplete; likely a conference paper or journal article].
Jafarzadeh Yeganeh, G. (2004). Identification of causes of delays in Azerbaijan power transmission lines projects and providing corrective solutions [Master’s thesis, University of Tehran].
Kamig, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (2016). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 34(1), 57–70. https://doi.org/10.1080/01446193.2016.1133915
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns. Building and Environment, 32(6), 509–516. https://doi.org/10.1016/S0360-1323(97)00027-8
Karer, M. (1992). Delays in Jordanian construction projects: Causes and solutions. Middle East Construction Review, 10(1), 89–102.
Molaei, A. (2012). Urban development project delays: Causes and solutions. Tehran, Iran: Urban Studies Journal.
Molaei, F., & Ghazanfarinia, H. (2006). Investigating the causes of delays in construction projects. In Proceedings of the 2nd International Conference on Project Management (pp. 203–214).
Molaei, R. (2012). Urban development delays: Challenges and solutions. Urban Studies Quarterly, 30(2), 145–160.
Mullah, F., & Ghazanfarinia, J. (2012). Investigating the causes of delays in construction projects with an overview of internal and external case studies. Mining and Development News and Information Base, 6(211), 2.
Osmond, H. (1957). Function as the basis of psychiatric ward design. New York, NY: Holt, Rinehart and Winston.
Rahman, M., Alavi, S., & Johnson, T. (2023). Sustainable practices in construction: Minimizing delays and environmental impact. Sustainable Development Journal, 15(1), 78–92. https://doi.org/10.1002/sd.2301
Rezazadeh, A. (2005). Investigating the causes of delays in dam projects and offering a proposal to reduce them [Master’s thesis, University of Tehran].
Rezazadeh, H. (2005). Using AHP to address delays in construction projects. Journal of Project Management, 12(3), 45–58.
Rezazadeh, S. (2005). Investigating the causes of increased delays in construction projects [Master’s thesis].
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007
Schumacher, L. (1995a). Delays in project execution: A comprehensive study. Project Management Journal, 26(2), 33–41.
Schumacher, L. (1995b). Project delays: Causes and mitigation strategies. Construction Management Journal, 12(2), 89–102.
Schumacher, L. (1995c). Quantifying and apportioning delay on construction projects. Cost Engineering, 37(2), 11–16.
Shakeri, A., & Ghorbani, A. (2005). Value engineering and management of claims and disputes in construction projects. In Proceedings of the 2nd Value Engineering Conference.
Sharif Zare, M. (2010). Study and analysis of the causes of project prolongation and determining the costs for the province, and providing appropriate solutions.
Sharifzadeh, M. (2010). Causes of delays in construction projects: A comprehensive analysis. Construction Research Journal, 22(1), 33–47.
Smith, J., & Johnson, T. (2022). Supply chain disruptions and their impact on construction timelines. Journal of Supply Chain Management, 40(4), 201–215. https://doi.org/10.1111/jscm.12245
Tibbalds, F. (1992). Making people-friendly towns: Improving the public environment in towns and cities. London, England: Spon Press.