Risk Assessment of Bridge Construction Project through cost management phases
Subject Areas : Risk AssessmentAbdulelah Ali 1 , Bader Al-Ablani 2 , Marwa Mekky 3 , Noura Al-Ghimlas 4 , Mohd Alam 5
1 - Department of Industrial Engineering, Jazan University, Jazan 45142, Saudi Arabia
2 - Mechanical Engineering Department, Faculty of Engineering, Benha University, Cairo, Egypt
3 - Department of Mechanical Design and Production Engineering, Cairo University, Giza, Egypt
4 - Department of Quantitative Methods and Information Systems, College of Business Administration, Kuwait University, Kuwait
5 - Department of Mechanical Engineering, Vivekananda Global University, Jaipur, Rajasthan
Keywords:
Abstract :
structural modeling: A new method for risks path identification
of the infrastructure projects,” in In Construction Research
Congress, Reston, VA, 2016. DOI:
10.1061/9780784479827.283
investigating he risk effects on schedule delay in infrastructure
projects,” J. Manage.Eng., vol. 33, no. 1, p. 04016029, 2017.
DOI: 10.1061/%28ASCE%29ME.1943-5479.0000472
Scheduling and Controlling, New Delhi: Tata McGraw-Hill
Publishing Company Limited, 2004.
cost estimates using factor analysis and multivariate
regression,” Journal of Construction Engineering and
Management, vol. 129, no. 2, pp. 198-204, 2003. DOI:
10.1061/(ASCE)0733-9364
project critical success factors for key construction players and
objectives,” Int. J. Eng., vol. 31, no. 2, p. 228–240, 2018. DOI:
10.5829/ije.2018.31.02b.06
Rostam, “Uncertainty management in time estimation of
construction projects: A systematic literature review and new
model development,” Sci. Iranica., vol. 26, no. 2, pp. 752-778,
2019. DOI: 10.24200/ SCI.2017.4605
[7] N. J. Smith, T. Merna and P. Jobling, Managing Risk in
Construction Projects, Wiley, 2014.
[8] T. Aven, “Risk assessment and risk management: Review of
recent advances on their foundation,” European Journal of
Operational Research, vol. 253, no. 1, p. 1–13, 2016. DOI:
10.1016/ j.ejor.2015.12.023
[9] T. Aven and B. S. Krohn, “A new perspective on how to
understand, assess and manage risk and the unforeseen,”
Reliability Engineering and System Safety , vol. 121, pp. 1-10,
2014. DOI: 10.1016/j.ress.2013.07.005
[10] J. R. Schuyler, Risk and decision analysis in projects,
Pennsylvania: Project Management Institute, 2001.
[11] V. M. R. Tummala and J. F. Burchett, “Applying a risk
management process (RMP) to manage cost risk for an EHV
transmission line project,” International Journal of Project
Management, vol. 17, no. 4, pp. 223-235, 1999. DOI:
10.1016/S0263-7863(98)00038-6
[12] A. S. Akintoye and M. J. MacLeod, “Risk analysis and
management in construction,” Int. J. Project Manage., vol. 15,
no. 1, p. 31–38, 1997. DOI: 10.1016/S0263-7863(96)00035-X
[13] R. C. Williams, J. A. Walker and A. J. Dorofee, “Putting risk
management into practice,” IEEE Software, vol. 14, no. 3, pp.
75-82, 1997. DOI: 10.1109/52.589240
[14] Y. Xia, Z. Xiong, X. Dong and H. Lu, “Risk assessment and
decision making under uncertainty in tunnel and underground
engineering,” Entropy, vol. 19, p. 549, 2017. DOI:
10.3390/e19100549
[15] R. M. Choudhry , M. A. Aslam, J. W. Hinze and F. M. Arain,
“Cost and schedule risk analysis of bridge construction in
Pakistan: Establishing risk guidelines,” J. Constr. Eng.
Manage., vol. 140, no. 7, p. 04014020, 2014. DOI:
10.1061/(ASCE)CO.1943-7862.0000857
[16] E. Gajewska and M. Ropel, “Risk Management Practices in a
Construction Projecta case study,” Göteborg, Sweden, 2011.
http://publications.lib.chalmers.se/records/fulltext/144253.pdf
[17] E. S. Hong, I. M. Lee, H. S. Shin, S. W. Nam and J. S. Kong,
“Quantitative risk evaluation based on event tree analysis
technique: Application to the design of shield TBM,” Tunn.
Undergr. Space Technol., vol. 24, pp. 269-277, 2009. DOI:
10.1016/j.tust.2008.09.004
[18] J. K. Vaurio, “Ideas and developments in importance measures
and fault-tree techniques for reliability and risk analysis,”
Reliab. Eng. Syst. Saf., vol. 95, pp. 99-107, 2010. DOI:
10.1016/j.ress.2009.08.006
[19] O. Špacková, J. Šejnoha and D. Straub, “Probabilistic
assessment of tunnel construction performance based on data,”
Tunn. Undergr. Space Technol., vol. 37, pp. 62-78, 2013. DOI:
10.1016/j.tust.2013.02.006
[20] S. K. Woo, K. J. Kim and T. H. Kim, “The Risk Factor
Analysis of Power Line Tunnel Using the AHP Method in
Construction Stage,” J. Korea Inst. Struct. Maint. Insp., vol. 17,
pp. 122-129, 2013. DOI: 10.11112/JKSMI.2013.17.5.122
[21] D. Wu, Q. Dai and X. Zhu, “Measuring the effect of project
risks based on Shapley value for project risk response,”
Procedia Computer Science, vol. 91, pp. 774-778, 2016. DOI:
10.1016/j.procs.2016.07.076
[22] T. Sato, “Risk-based project value – the definition and
applications to decision,” making, Procedia – Social and
Behavioural Sciences, vol. 119, pp. 152-161, 2014. DOI:
0.1016/j.sbspro.2014.03.019
[23] R. L. Sousa and H. H. Einstein, “Risk analysis during tunnel
construction using Bayesian Networks: Porto Metro case
study,” Tunn. Undergr. Space Technol., vol. 27, pp. 86-100,
2012. DOI: 10.1016/j.tust.2011.07.003
[24] A. Nieto-Morote and F. Ruz-Vila, “A fuzzy approach to
construction project risk assessment,” Int. J. Proj. Manag., vol.
29, pp. 220-231, 2011. DOI: 10.1016/j.ijproman.2010.02.002
[25] M.S. Kirkire, S.B. Rane and J.R. Jadhav, “Risk management in
medical product development process using traditional FMEA
and fuzzy linguistic approach: A case study,” Journal of
Industrial Engineering International., vol. 11, pp. 595-611,
2015. DOI: 10.1007/s40092-015-0113-y
[26] R. C. Walke and V. M. Topkar, “An Approach to risk
quantification in construction projects using EMV analysis,”
International Journal of Engineering Science and Technology,
vol. 3, no. 9, pp. 6847-6855, 2011. https://www.idc-
online.com/technical_references/pdfs/ civil_
engineering/An%20Approach.pdf
[27] K. Rezaie, M. S. Amalnik, A. Gereie and B. Ostadi, “Using
extended Monte Carlo simulation method for the improvement
of risk management: Consideration of relationships between
uncertainties,” Appl. Math. Comput., vol. 190, pp. 1492-1501,
2007. DOI: 10.1016/j.amc.2007.02.038
[28] M.M. Khadem, S.Piya, and A. Shamsuzzoha, “Quantitative risk
management in gas injection project: a case study from Oman
oil and gas industry,” Journal of Industrial Engineering
International., vol. 14, pp. 637-654, 2018. DOI:
10.1007/s40092-017-0237-3
[29] R. S. Heralova, “Possibility of Using Value Engineering in
Highway Projects,” Procedia Engineering, vol. 164, pp. 362-
367, 2016. DOI: 10.1016/j.proeng.2016.11.631
[30] T. R. Browning, “A Quantitative Framework for Managing
Project Value, Risk, and Opportunity,” IEEE Transactions on
Engineering Management , vol. 61, no. 4, pp. 583-598, 2014.
DOI: 10.1109/TEM.2014.2326986
[31] A. Terje and R. Ortwin, “On risk defined as an event where the
outcome is uncertain,” J. Risk Res., vol. 12, pp. 1-11, 2009.
DOI: 10.1080/13669870802488883
[32] C. L. Berner and R. Flage, “Creating risk management
strategies based on uncertain assumptions and aspects from
assumption-based planning,” Reliab. Eng. Syst. Saf., vol. 167,
pp. 10-19, 2017. DOI: 10.1016/j.ress.2017.05.009
[33] T. Aven, “Practical implications of the new risk perspectives,”
Reliab. Eng. Syst. Saf., vol. 115, pp. 136-145, 2013. DOI:
10.1016/j.ress.2013.02.020
[34] J. Shortridge, T. Aven and S. Guikem, “Risk assessment under
deep uncertainty: A methodological comparison,” Reliability
Engineering and System Safety, vol. 159, pp. 12-23, 2017. DOI:
10.1016/j.ress.2016.10.017
[35] P. R. Rose, “Risk Analysis and Management of Petroleum
Exploration Ventures,” Tulsa, 2001. DOI: 10.1306/Mth12792
[36] E. T. Brown, “Risk assessment and management in
underground rock engineering—An overview,” Journal of
Rock Mechanics and Geotechnical Engineering, vol. 4, no. 3,
pp. 193-204, 2012. DOI: 10.3724/SP.J.1235.2012.00193
[37] S. S. Rao and L. Cao, “Optimum Design of Mechanical
Systems Involving Interval Parameters,” J. Mech. Des., vol.
124, pp. 465-472, 2002. DOI: 10.1115/1.1479691
[38] A. A. Alola, M. Tunay and V. Alola, “Analysis of Possibility
Theory for Reasoning under Uncertainty,” Int. J. Stat. Probab.,
vol. 2, pp. 171-180, 2013. DOI: 10.5539/ijsp.v2n2p12
[39] K. Zaman, S. Rangavajhala, M. P. Mcdonald and S.
Mahadevan, “A probabilistic approach for representation of
interval uncertainty,” Reliab. Eng. Syst. Saf., vol. 96, pp. 117-
130, 2011. DOI: 10.1016/j.ress.2010.07.012
[40] H. C. Abou and A. Ashi, “Comparative analysis of design/build
and design/bid/build project delivery systems in Lebanon,”
Journal of Industrial Engineering International. vol. 15, pp.
147-152, 2019. DOI: 10.1007/s40092-019-00323-1