Prioritization of Delay Causes in Rural Road Construction Projects
محورهای موضوعی : Journal of Building Information ModelingEnsiye Moradi 1 , Mina Kheyrandish 2
1 - Department of civil Engineering, Shi. C, Islamic Azad University, Shiraz, Iran
2 - Shi. C, Islamic Azad University, Shiraz, Iran
کلید واژه: Multiple criteria analysis, Project delay, Rural Road construction, DEMATEL, ANP,
چکیده مقاله :
Delays are a common and integral part of construction projects, despite their undesirable impact on costs. Several studies in the existing body of knowledge have already advocated different strategies to minimize project delays, abandonment, and cost overruns. However, existing studies have predominantly focused on urban projects, thereby depriving us of knowledge of rural projects despite their peculiarities. Therefore, the overarching aim of this study is to identify and prioritize the causes of delays in rural road construction projects in Iran, and to investigate the relationships among them using a hybrid DEMATEL-ANP decision-making framework. According to the results, "financial problems" have the most interactions with other indicators, while "inflation" is identified as the factor with the most significant influence on other indicators. Furthermore, results depict that "lack of credits" is the most effective and influential leading cause of delays in rural road construction projects. It was also indicated that initially anticipated project funds are much lower than the actual costs, due to inflation in Iran. Results obtained through can aid the recognition of the most prevalent causes of rural projects, while still accounting for the peculiarities of such projects, so that project owners can improve the robustness of planning for future projects.
Delays are a common and integral part of construction projects, despite their undesirable impact on costs. Several studies in the existing body of knowledge have already advocated different strategies to minimize project delays, abandonment, and cost overruns. However, existing studies have predominantly focused on urban projects, thereby depriving us of knowledge of rural projects despite their peculiarities. Therefore, the overarching aim of this study is to identify and prioritize the causes of delays in rural road construction projects in Iran, and to investigate the relationships among them using a hybrid DEMATEL-ANP decision-making framework. According to the results, "financial problems" have the most interactions with other indicators, while "inflation" is identified as the factor with the most significant influence on other indicators. Furthermore, results depict that "lack of credits" is the most effective and influential leading cause of delays in rural road construction projects. It was also indicated that initially anticipated project funds are much lower than the actual costs, due to inflation in Iran. Results obtained through can aid the recognition of the most prevalent causes of rural projects, while still accounting for the peculiarities of such projects, so that project owners can improve the robustness of planning for future projects.
Agumba, J. N. (2016). A review of the challenges of rural road network development. In: Bingley: Emerald Publishing Limited.
Alsuliman, J. A. (2019). Causes of delay in Saudi public construction projects. Alexandria Engineering Journal, 58(2), 801–808. https://doi.org/https://doi.org/10.1016/j.aej.2019.07.002 .
Amare, Y., Quezon, E. T., & Busier, M. (2017). Causes of delays during the construction phase of road projects due to the failures of the contractor, consultant, and employer in the Addis Ababa City Road Authority. International Journal of Scientific & Engineering Research, 8(3), 15–25.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Aziz, R. F., & Abdel-Hakam, A. A. (2016). Exploring the causes of road construction projects in Egypt. Alexandria Engineering Journal, 55(2), 1515–1539. https://doi.org/https://doi.org/10.1016/j.aej.2016.03.006
Balali, A., Valipour, A., Edwards, R., & Moehler, R. (2021). Ranking effective risks on human resources threats in natural gas supply projects using the ANP-COPRAS method: Case study of Shiraz: reliability Engineering & System Safety, 208, 107442.https://doi.org/10.1016/j.ress.2021.107442
Brožová, H., & Růžička, M. (2010). The AHP and ANP models for transport environmental impacts assessment. WSEAS Trans. Power Syst, 5, 233–242.
Durdyev, S., & Hosseini, M. R. (2019). Causes of delays on construction projects: a comprehensive list. International Journal of Managing Projects in Business, 13(1), 20–46. https://doi.org/10.1108/IJMPB-09-2018-0178
Fontela, E., & Gabus, A. (1974). DEMATEL: Progress achieved. In: Pergamon.
Gunduz, M. (2016). Causes of Construction Delays in Qatar Construction Projects.
Habibi, M., Kermanshachi, S., & Safapour, E. (2018). Engineering, procurement, and construction cost and schedule performance leading indicators: state-of-the-art review. Proceedings of Construction Research Congress,
Hasnain, M., Thaheem, M. J., & Ullah, F. (2018). Best value contractor selection in road construction projects: ANP-based decision support system. International Journal of Civil Engineering, 16(6), 695–714.
Hatefi, S. M., & Tamošaitienė, J. (2019). An integrated fuzzy DEMATEL-fuzzy ANP model for evaluating construction projects by considering interrelationships among risk factors. Journal of Civil Engineering and Management, 25(2), 114–131. https://doi.org/10.3846/jcem.2019.8280
Hu, H.-Y., Lee, Y.-C., Yen, T.-M., & Tsai, C.-H. (2009). Using BPNN and DEMATEL to modify the importance–performance analysis model – A study of the computer industry. Expert Systems with Applications, 36(6), 9969–9979. https://doi.org/10.1016/j.eswa.2009.01.062
Ji, Y., Qi, L., Liu, Y., Liu, X., Li, H. X., & Li, Y. (2018). Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China. Applied Sciences, 8, 2324. https://doi.org/10.3390/app8112324
Khair, K., Mohamed, Z., Mohammad, R., Farouk, H., & Ahmed, M. E. (2018). A Management Framework to Reduce Delays in Road Construction Projects in Sudan. Arabian Journal for Science and Engineering, 43(4), 1925–1940. https://doi.org/10.1007/s13369-017-2806-6
Kumar, V. (2020). Delay in Construction of Highway and Expressway Projects. International Research Journal of Engineering and Technology (IRJET) 07(06).
Lozano Serna, S., Patiño Galindo, I., Gómez-Cabrera, A., & Torres, A. (2018). Identifying Factors Causing Delays and Cost Overruns in Construction Projects in Colombia. Ingeniería y Ciencia, 14(27), 117–151. https://doi.org/10.17230/ingciencia.14.27.6
Mahamid, I. (2017). Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants, and Effects.
Mahdi, I., & Soliman, E. (2018). Significant and top-ranked delay factors in the Arab Gulf countries. International Journal of Construction Management, 18. https://doi.org/10.1080/15623599.2018.1512029
Menesi, W. (2007). Construction delay analysis under multiple baseline updates, University of Waterloo.
Ochieng, E. G., Mpofu, B., Pretorius, A., & Moobela, C. (2017). Profiling causative factors leading to construction project delays in the United Arab Emirates. Engineering, Construction and Architectural Management, 24(2), 346–376. https://doi.org/10.1108/ECAM-05-2015-0072
Plebankiewicz, E. (2018). Model of Predicting Cost Overrun in Construction Projects. Sustainability, 10(12). https://doi.org/10.3390/su10124387
Ramli, M., Malek, M., Hanipah, M., Lin, C., Sukri, M. M., Zawawi, M., Abidin, M. Z., & Fuad, N. M. (2018). Study of factors influencing construction delays in rural areas in Malaysia. Journal of Physics: Conference Series, 10.1088/1742-6596/1049/1/012017
Saaty, T. L., & Vargas, L. G. (2006). Decision-making with the Analytic Hierarchy Process (Vol. 282). Springer.
Santoso, D. S., & Soeng, S. (2016). Analyzing Delays of Road Construction Projects in Cambodia: Causes and Effects. Journal of Management in Engineering, 32(6), 05016020. https://doi.org/doi:10.1061/(ASCE)ME.1943-5479.0000467
Shehu, Z., Endut, I., Akintoye, A., & Holt, G. (2014). Analysis of characteristics affecting completion time for Malaysian construction projects. Built Environment Project and Asset Management, 5, 52–68. https://doi.org/10.1108/BEPAM-10-2013-0056
Tadewos, S. G., & Patel, D. (2018). Factors influencing Time and Cost Overruns in Road Construction Projects: Addis Ababa, Ethiopian Scenario: Review paper.
Thapanont, P., Santi, C., & Pruethipong, X. (2018). Causes of delay on highway construction projects in Thailand. MATEC Web of Conferences, 192, 02014. https://doi.org/10.1051/matecconf/201819202014
Valipour, A., Yahaya, N., Md Noor, N., Kildienė, S., Sarvari, H., & Mardani, A. (2015). A fuzzy analytic network process method for risk prioritization in freeway PPP projects: an Iranian case study. Journal of Civil Engineering and Management, 21(7), 933–947. https://doi.org/10.3846/13923730.2015.1051104
Venkatesh, P., & Venkatesan, V. (2019). Delays in construction projects: A review of causes, need & scope for further research DELAYS IN CONSTRUCTION PROJECTS: A REVIEW OF CAUSES, NEED AND SCOPE FOR FURTHER RESEARCH.
Yap, J. B. H., & Skitmore, M. (2018). Investigating design changes in Malaysian building projects. Architectural Engineering and Design Management, 14(3), 218–238. https://doi.org/10.1080/17452007.2017.1384714