Study of development cycle of down ramp in underground metal mine
الموضوعات :
Nirlipta Nayak
1
,
Harinandan Kumar
2
,
Suhel Ahmed
3
1 - Department of Petroleum Engineering and Earth Sciences, University of Petroleum and Energy Studies, Bidholi, Via Prem Nagar, Dehradun, Uttarakhand 248007, India
2 - Department of Petroleum Engineering and Earth Sciences, University of Petroleum and Energy Studies, Bidholi, Via Prem Nagar, Dehradun, Uttarakhand 248007, India
3 - Department of Petroleum Engineering and Earth Sciences, University of Petroleum and Energy Studies, Bidholi, Via Prem Nagar, Dehradun, Uttarakhand 248007, India
تاريخ الإرسال : 25 الخميس , شوال, 1443
تاريخ التأكيد : 03 الجمعة , ربيع الثاني, 1444
تاريخ الإصدار : 16 الأحد , ربيع الأول, 1445
الکلمات المفتاحية:
Development cycle,
Delays,
development operations,
Blast cycle optimization,
ملخص المقالة :
Mine development is the process of constructing a mining facility and supporting infrastructure. In the mining industry, operations are sequential. It means one function cannot start until its preceding operation has been completed. Hence, a delay in any operations results in an overall delay for the total target. Effective underground mine planning aims at least idle & breakdown time. One such delay examined here is the cycle time for the developments in headings and drives. In this study, Blast-to-blast cycle time was evaluated in terms of productive and unproductive work in Indian underground metal mines. The actual Average Cycle Time for blast-to-blast operations was observed at 37.12 hrs, higher than the expected Cycle Time, i.e., 12.16 hrs. The variation in cycle time leads to the delay. Therefore, a study was carried out to determine the actual cause of delay through real-time analysis of all the operations during the development. The delays were breakdown, manpower idle time, shift problem, poor ventilation, water pressure problem, etc. reduced work time utilization, dewatering, and pump breakdown were observed as significant factors for cycle time delays. Effective measures were suggested to optimize the cycle time by controlling the factors responsible for the delay and improving the development cycle.
المصادر:
Cuie JD, Chai YT (2017) Recent Progress on Data-Based Optimization for Mineral Processing Plants, Engineering 3: 183-187.
Dehghan AN, Yazdi A (2023) A Geomechanical Investigation for Optimizing the Ultimate Slope Design of Shadan Open Pit Mine, Iran, Indian Geotechnical Journal 1-15.
Dougall W and Mmola TM (2015) Identification of key performance areas in the southern African surface mining delivery environment, Journal of the southern African Institute of mining and metallurgy 15: 1001-1006.
Jedrzejczyk A, Byrdy A, Firek K, and Rusek J (2022) Partial Least Squares Regression Approach in the Analysis of Damage Intensity Changes to Prefabricated RC Buildings during the Long Term of Mining Activity, Applied Sciences 12: 467-480.
Karimiazar J, SharifiTeshnizi E, O'Kelly BC, SadeghiSh, Karimizad N, Yazdi A, Arjmandzadeh R (2023) Effect of Nano-Silica on Engineering Properties of Lime-Treated Marl Soil, Transportation Geotechnics 43, 101123
Khazaei S, Pourrahimian Y (2021) Mathematical Programming Application in Sublevel Caving Production Scheduling. Mining 1: 180-191.
Kowalska J (2018) Method for Assessing the Development of Underground Hard Coal Mines on a Regional Basis: The Concept of Measurement and Research Results, Energies 11: 1370-1393.
Maus V, Giljum S, Gutschlhofer J, Silva DMD, Probst M, Gass SLB, Luckeneder S, Lieber M, McCallum I (2020) A global-scale data set of mining areas, Scientific Data 7: 289.
Musingwini (2016) Presidential Address: Optimization in Underground Mine Planning- Development and opportunities. The Journal of South African Institute of Mining and Metallurgy 16: 809-811.
Rao KK, Chaudahry BS, Ghade A and Chandrahas (2020) Critical analysis of process cycle by numerical modelling for faster development of drives in hard-rock underground mine – a case study, Current Science 118: 1547-1556.
Shehu G, Koki B (2019) Application of Multivariate Analysis in the Evaluation of Metals Distribution in Soil from Awwal Mining Site Kebbi, Nigeria, Nigerian Journal of Basic and Applied Science 27: 17-24.
Singh SP (2018) Overbreak control in underground mines, Rock Mech Open Access J 1(1):11-17.
Zhang H, Li T, Wu S, Zhang X, Gao W, Shi Q (2022) A study of innovative cut blasting for rock roadway excavation based on numerical simulation and field tests, Tunnelling and Underground Space Technology 119: 104233.